With the ball - packing 45 replacement

(1) close valves on the block valves upstream and downstream. Put the gas pipeline of unloading valve and pressure.
(2) make ball valve is in full close state.
(3) shake off nut 52, remove the gasket 75, 74 and handle 47 head wrench.
(4) shake off nut 48, remove the spring washers, 49, stem spacing device 66 and packing gland 50.
(5) remove packing 45.
(6) removed parts, check if there is damage repair or replacement, all parts will be clean.
(7) scrubbing and lubrication sealing filler letter.
(8) into the new packing 45.
(9) according to the decomposition of inverse sequence on packing gland 50, stem spacing device 66, spring washer 49, with 48 solid tight these parts nuts.
(10) the first 74 and handle 47 wrench, mount gasket 75, with 52 fixed tightly. Nuts,
(11) check valve handles the shutoff flexibility.
(12) Air tightness test

The ball with gear box packing 45 - the replacement

(1) close valves on the block valves upstream and downstream. Put the gas pipeline and the unloading valve pressure.
(2) make ball valve is in full close state.
(3) shake off, remove the screw 10 gear box.
(4) shake off 15, remove the screw driver flange 34.
(5) shake off nut 48, remove the spring washers 49 and packing gland 50, packing 45.
(6) removed parts, check if there is damage, repair or replacement, all parts will be clean.
(7) cleaning and lubrication sealing filler letter.
(8) into the new packing 45.
(9) according to the decomposition of inverse sequence on packing gland 50, spring washer 49, with 48 solid tight these parts nuts. The actuator flange bolts and solid with tight.
(10) on gear box, fixed tightly with screws 10.
(11) check valve operating gearbox flexibility.
(12)Air tightness test.

With pneumatic drive the ball - 40 and packing o-rings 56, 112 replacement

(1) close valves on the block valves upstream and downstream. Put the gas pipeline and the unloading valve pressure.
(2) make ball valve is in full close state. Demolition pneumatic pipe.
(3) shake off screw driver and 35 will drive flange. Together,
(4) take the keys on the stem, twist off 15 November, remove the screw packing gland 33, packing, 40.
(5) from the packing gland extracted o-rings 56 and 112.
(6) removed parts, check if there is damage repair or replacement, all parts will be clean.
(7) cleaning and lubrication stuffing box sealing and o-rings installed slot.
(8) into the new packing 40, load new o-rings 56 and 112.
(9) mount gland with 33, screw, on 15 solid key 11.
(10) will drive flange and drive along with screw mounted, 35 solid tight.
(11), connected to the pneumatic pipe operating drives check shutoff flexibility.
(12)Air tightness test.

Shanghai MeiYan Yi Pump & Valve Co., Ltd.
MeiYan Yi ball valve Contact MeiYan Yi
Shanghai Enine Pump & Valve Co., Ltd.
Enine ball valve Contact Enine
Shanghai Saitai Pump & Valve CO., Lid.
Saitai ball valve Contact Saitai
Shanghai Fengqi Industrial Development Co., Ltd.
FengQi ball valve Contact FengQi